With winter clearly upon us the Route 12 project is slowing down for the season. The hot mix asphalt layer has been completed from Bemis Road to Nichols Street, including Carey Street and Old Leominster Road, with only temporary striping left to do. In some places temporary asphalt sidewalks have been put in for the winter as it had become too cold to pour concrete. Some signal work may still be completed in upcoming months but road construction will not resume until spring. If you have any questions or concerns contact Jessica at (978) 353-7600 extension 241
11/19/07 to 11/30/07 At the present time A. F. Amorello & Sons (Amorello) is scheduled to continue working on the widening on Route 12 from Wanoosnoc Road to Benson Street. This widening consists of excavation, retaining wall construction, granite curbing, concrete sidewalks, and hot mix asphalt pavement. Amorello will also continue working on the full depth pavement section from Benson Street to Nichols Street.
11/27/07 & 11/28/07 Amorello will be doing the asphalt pavement excavation by milling from Bemis Road to Benson Street.
The hot mix asphalt (binder) layer is scheduled to be completed from Bemis Road to Nichols Street by December 7, 2007.